| Action Date | Action Description | 
|---|---|
| Oct 12, 2012 | Dredge Application | 
| Oct 15, 2012 | Administrative Review for Completeness | 
| Oct 15, 2012 | Team Review for Completeness | 
| Oct 15, 2012 | Application Accepted | 
| Oct 24, 2012 | Joint Public Notice | 
| Oct 25, 2012 | HPHC Historical Preservation No Effect | 
| Nov 20, 2012 | Dredge Report | 
| Nov 20, 2012 | DEM Dredge Permit | 
| Nov 26, 2012 | Typist for Processing | 
| Nov 26, 2012 | Site Inspection | 
| Nov 26, 2012 | Permit Issued | 
| Nov 27, 2012 | Executive Sign Off | 
| Nov 27, 2012 | Sent to Photo Copy | 
| Nov 30, 2012 | US Army Corps of Engineers Approval Received | 
| Jan 28, 2013 | Site Inspection | 
| Jan 28, 2013 | Site Inspection | 
| Feb 22, 2013 | Correspondence Mailed/Faxed/E-mailed | 
| Apr 24, 2013 | CAD Cell Fee Due-Final |