| Action Date | Action Description |
|---|---|
| Nov 20, 2012 | Freshwater Wetland - Preliminary Determination |
| Nov 20, 2012 | Administrative Review for Completeness |
| Jan 09, 2013 | Team Review for Completeness |
| Jan 09, 2013 | Team Review for Completeness |
| Jan 09, 2013 | Application Accepted |
| Feb 05, 2013 | Additional Information Received |
| Feb 12, 2013 | Biologist Report |
| Feb 12, 2013 | Engineering Report |
| Feb 13, 2013 | Typist for Processing |
| Feb 14, 2013 | Executive Sign Off |
| Feb 14, 2013 | Sent to Photo Copy |
| Feb 14, 2013 | Permit Issued |
| Feb 22, 2013 | Land Evidence Date |