| Action Date | Action Description |
|---|---|
| Mar 04, 2013 | Assent Application Received |
| Mar 05, 2013 | Administrative Review for Completeness |
| Mar 06, 2013 | Team Review for Completeness |
| Mar 06, 2013 | Application Accepted |
| Mar 15, 2013 | Biologist Report |
| Mar 19, 2013 | Typist for Processing |
| Mar 21, 2013 | HPHC Historical Preservation No Effect |
| Mar 25, 2013 | Executive Sign Off |
| Mar 25, 2013 | Sent to Photo Copy |
| Mar 25, 2013 | Permit Issued |
| Jul 26, 2013 | Land Evidence Date |
| Aug 02, 2013 | Phone Call |
| Dec 03, 2014 | Modification Request |
| Dec 04, 2014 | Administrative Review for Completeness |
| Dec 05, 2014 | Team Review for Completeness |
| Dec 11, 2014 | Biologist Report |
| Dec 18, 2014 | Typist for Processing |
| Dec 18, 2014 | Modification Approved |
| Dec 19, 2014 | Executive Sign Off |
| Dec 19, 2014 | Sent to Photo Copy |
| Dec 08, 2015 | Land Evidence Date |