| Action Date | Action Description |
|---|---|
| Mar 11, 2013 | Assent Application Received |
| Mar 11, 2013 | Administrative Review for Completeness |
| Mar 13, 2013 | Team Review for Completeness |
| Mar 13, 2013 | Team Review for Completeness |
| Mar 13, 2013 | Application Accepted |
| Apr 02, 2013 | 30 day Public Notice Issued |
| Apr 05, 2013 | HPHC Historical Preservation No Effect |
| Apr 13, 2013 | HPHC Historical Preservation No Effect |
| May 01, 2013 | Objections/Comments Received |
| May 02, 2013 | Public Notice End Date |
| May 22, 2013 | Additional Information Received |
| Jul 01, 2013 | Correspondence Received |
| Jul 16, 2013 | Biologist Report |
| Jul 16, 2013 | Engineering Report |
| Jul 17, 2013 | Supervisor Biologist SignOff |
| Jul 17, 2013 | Executive Signoff of Staff Reports |
| Aug 07, 2013 | Correspondence Received |
| Aug 14, 2013 | Ready to Schedule Semi-Monthly Meeting |
| Aug 14, 2013 | Mail Agenda Notice |
| Aug 27, 2013 | Semi-Monthly Meeting Date Scheduled |
| Sep 17, 2013 | Mail Agenda Notice |
| Sep 17, 2013 | Ready to Schedule Semi-Monthly Meeting |
| Sep 24, 2013 | Semi-Monthly Meeting Date Scheduled |
| Sep 24, 2013 | Semi-Monthly Meeting Held |
| Sep 24, 2013 | Council Approval Granted |
| Oct 08, 2013 | Legal Response/Decision |
| Oct 16, 2013 | 30 Day Appeal Notification to Owner |
| Nov 04, 2013 | Additional Information Received |
| Nov 15, 2013 | Stipulation Package from Biologist |
| Nov 15, 2013 | Stipulation Package by Engineer |
| Nov 19, 2013 | Typist for Processing |
| Nov 19, 2013 | Executive Sign Off |
| Nov 19, 2013 | Sent to Photo Copy |
| Nov 19, 2013 | Permit Issued |
| Dec 02, 2013 | Land Evidence Date |