| Action Date | Action Description |
|---|---|
| Apr 04, 2013 | Assent Application Received |
| Apr 07, 2013 | Administrative Review for Completeness |
| May 06, 2013 | Deficient Application - Owner Notification Sent |
| May 17, 2013 | Deficiency Response Received |
| Jun 06, 2013 | Team Review for Completeness |
| Jun 06, 2013 | Team Review for Completeness |
| Jun 06, 2013 | Application Accepted |
| Jun 11, 2013 | 30 day Public Notice Issued |
| Jul 01, 2013 | Plans Received |
| Jul 09, 2013 | Objections/Comments Received |
| Jul 11, 2013 | Public Notice End Date |
| Jul 22, 2013 | HPHC Historical Preservation No Effect |
| Dec 19, 2013 | 30-Day Notification of Cancellation letter |
| Dec 20, 2013 | Certified Receipt Received |
| Jan 16, 2014 | Additional Information Received |
| Jan 28, 2014 | Plans Received |
| Jan 28, 2014 | Biologist Report |
| Jan 31, 2014 | Supervisor Biologist SignOff |
| Jan 31, 2014 | Supervisor Engineer SignOff |
| Jan 31, 2014 | Executive Signoff of Staff Reports |
| Feb 18, 2014 | Mail Agenda Notice |
| Feb 24, 2014 | US Army Corps of Engineers Approval Received |
| Feb 25, 2014 | Council Approval Granted |
| Feb 25, 2014 | Semi-Monthly Meeting Held |
| Feb 25, 2014 | Semi-Monthly Meeting Date Scheduled |
| Feb 26, 2014 | Stipulation Package from Biologist |
| Mar 10, 2014 | Legal Response/Decision |
| Mar 10, 2014 | 30 Day Appeal Notification to Owner |
| Mar 12, 2014 | Typist for Processing |
| Mar 12, 2014 | Permit Issued |
| Mar 13, 2014 | Executive Sign Off |
| Mar 13, 2014 | Sent to Photo Copy |
| May 02, 2014 | Land Evidence Date |