| Action Date | Action Description |
|---|---|
| Apr 10, 2013 | Assent Application Received |
| Apr 10, 2013 | Administrative Review for Completeness |
| Apr 15, 2013 | Fee Waiver Granted |
| Apr 19, 2013 | Team Review for Completeness |
| Apr 19, 2013 | Application Accepted |
| Apr 30, 2013 | HPHC Historical Preservation No Effect |
| May 28, 2013 | Water Quality Certification |
| Jul 10, 2013 | Biologist Report |
| Jul 15, 2013 | Typist for Processing |
| Jul 15, 2013 | Executive Sign Off |
| Jul 15, 2013 | Sent to Photo Copy |
| Jul 15, 2013 | Permit Issued |
| Jul 25, 2013 | US Army Corps of Engineers Approval Received |
| Dec 10, 2014 | Commencement of Work Notice received |
| Dec 11, 2014 | Modification Request |
| Dec 11, 2014 | Report completed |
| Dec 12, 2014 | Policy Review |
| Dec 12, 2014 | Correspondence Received |
| Dec 18, 2014 | Typist for Processing |
| Dec 18, 2014 | Executive Sign Off |
| Dec 18, 2014 | Sent to Photo Copy |
| Dec 18, 2014 | Modification Approved |