| Action Date | Action Description |
|---|---|
| Apr 23, 2013 | Assent Application Received |
| Apr 23, 2013 | Administrative Review for Completeness |
| Apr 30, 2013 | Team Review for Completeness |
| Apr 30, 2013 | Team Review for Completeness |
| Apr 30, 2013 | Application Accepted |
| May 10, 2013 | HPHC Historical Preservation No Effect |
| Jun 03, 2013 | Policy Review |
| Jun 04, 2013 | Typist for Processing |
| Jun 04, 2013 | Permit Issued |
| Jun 07, 2013 | Executive Sign Off |
| Jun 07, 2013 | Sent to Photo Copy |
| Jul 12, 2013 | US Army Corps of Engineers Approval Received |
| Sep 09, 2013 | Commencement of Work Notice received |
| Mar 28, 2014 | Modification Request |
| Mar 31, 2014 | Administrative Review for Completeness |
| Apr 04, 2014 | Team Review for Completeness |
| Apr 07, 2014 | Policy Review |
| Apr 11, 2014 | Typist for Processing |
| Apr 11, 2014 | Modification Approved |
| Apr 14, 2014 | Executive Sign Off |
| Apr 14, 2014 | Sent to Photo Copy |
| May 15, 2014 | Land Evidence Date |