| Action Date | Action Description |
|---|---|
| Apr 26, 2013 | Assent Application Received |
| May 06, 2013 | Administrative Review for Completeness |
| May 06, 2013 | Application Accepted |
| May 06, 2013 | Engineering Report |
| May 06, 2013 | Typist for Processing |
| May 08, 2013 | Executive Sign Off |
| May 08, 2013 | Sent to Photo Copy |
| May 09, 2013 | Permit Issued |
| Apr 22, 2016 | Extension of Permit Request |
| Apr 25, 2016 | Extension Toll letter mailed |