| Action Date | Action Description |
|---|---|
| HPHC Historical Preservation No Effect | |
| Feb 20, 2015 | Assent Application Received |
| Feb 23, 2015 | Administrative Review for Completeness |
| Feb 24, 2015 | Team Review for Completeness |
| Feb 24, 2015 | Deficient Application - Owner Notification Sent |
| Mar 20, 2015 | Correspondence Received |
| Apr 13, 2015 | Deficient Application Picked Up |
| May 11, 2015 | Deficiency Response Received |
| May 13, 2015 | Team Review for Completeness |
| May 13, 2015 | Application Accepted |
| May 21, 2015 | 30 day Public Notice Issued |
| Jun 18, 2015 | Objections/Comments Received |
| Jun 19, 2015 | Objections/Comments Received |
| Sep 11, 2015 | Correspondence Received |
| Nov 05, 2015 | Correspondence Received |
| Dec 30, 2015 | Category A* (Docks) |
| Jan 04, 2016 | Letter of Support for Project |
| Jan 12, 2016 | Mail Agenda Notice |
| Jan 15, 2016 | Plans Received |
| Jan 20, 2016 | Biologist Report |
| Jan 21, 2016 | Supervisor Biologist SignOff |
| Jan 21, 2016 | Supervisor Engineer SignOff |
| Jan 21, 2016 | Executive Signoff of Staff Reports |
| Jan 25, 2016 | Correspondence Received |
| Jan 26, 2016 | Council Approval Granted |
| Jan 26, 2016 | Semi-Monthly Meeting Date Scheduled |
| Feb 03, 2016 | Legal Response/Decision |
| Feb 03, 2016 | 30 Day Appeal Notification to Owner |
| Mar 09, 2016 | Plans Received |
| Mar 15, 2016 | US Army Corps of Engineers Approval Received |
| May 20, 2016 | Additional Information Received |
| May 20, 2016 | Stipulation Package from Biologist |
| May 27, 2016 | Typist for Processing |
| May 27, 2016 | Executive Sign Off |
| May 27, 2016 | Sent to Photo Copy |
| May 27, 2016 | Permit Issued |
| Jun 21, 2016 | Land Evidence Date |
| Sep 29, 2016 | Plans Received |
| Sep 30, 2016 | Plans Received |
| Oct 21, 2016 | Assent Correction Mailed |
| Oct 24, 2016 | Correspondence Received |
| Nov 01, 2017 | Correspondence Received |
| Nov 01, 2017 | Modification Request |
| Nov 02, 2017 | Application Accepted |
| Nov 16, 2017 | Biologist Report |
| Nov 20, 2017 | Modification Approved |
| Dec 19, 2017 | Land Evidence Date |