| Action Date | Action Description |
|---|---|
| HPHC Historical Preservation No Effect | |
| Oct 19, 2015 | Assent Application Received |
| Oct 20, 2015 | Administrative Review for Completeness |
| Oct 21, 2015 | Team Review for Completeness |
| Oct 21, 2015 | Team Review for Completeness |
| Oct 21, 2015 | Application Accepted |
| Oct 21, 2015 | Biologist Report |
| Oct 21, 2015 | Engineering Report |
| Oct 21, 2015 | Engineering Report |
| Dec 03, 2015 | 30 day Public Notice Issued |
| Dec 30, 2015 | Category A* (Docks) |
| Jan 03, 2016 | Public Notice End Date |
| Jan 15, 2016 | Objections/Comments Received |
| Jan 22, 2016 | Public Notice End Date Extension Granted |
| Feb 01, 2016 | US Army Corps of Engineers Approval Received |
| Feb 08, 2016 | Plans Received |
| Feb 22, 2016 | Typist for Processing |
| Feb 24, 2016 | Executive Sign Off |
| Feb 24, 2016 | Sent to Photo Copy |
| Feb 24, 2016 | Permit Issued |
| Mar 04, 2016 | Land Evidence Date |