| Action Date | Action Description |
|---|---|
| Nov 10, 2015 | Team Review for Completeness |
| Nov 10, 2015 | Assent Application Received |
| Nov 10, 2015 | Administrative Review for Completeness |
| Nov 13, 2015 | Team Review for Completeness |
| Nov 13, 2015 | Application Accepted |
| Nov 20, 2015 | 30 day Public Notice Issued |
| Dec 20, 2015 | Public Notice End Date |
| Dec 21, 2015 | Objections/Comments Received |
| Dec 28, 2015 | HPHC Historical Preservation No Effect |
| Jan 13, 2016 | Correspondence Received |
| Feb 01, 2016 | Public Hearing Notices Mailed |
| Feb 08, 2016 | Notice Advertisement confirmation |
| Feb 26, 2016 | Supervisor Engineer SignOff |
| Feb 26, 2016 | Engineering Report |
| Feb 29, 2016 | Executive Signoff of Staff Reports |
| Mar 08, 2016 | Council Approval Granted |
| Mar 08, 2016 | Semi-Monthly Meeting Date Scheduled |
| Apr 13, 2016 | Stipulation Package by Engineer |
| Apr 13, 2016 | Legal Response/Decision |
| Apr 20, 2016 | Typist for Processing |
| Apr 20, 2016 | Category B assigned |
| Apr 21, 2016 | Executive Sign Off |
| Apr 21, 2016 | Sent to Photo Copy |
| Apr 21, 2016 | Permit Issued |
| Apr 25, 2016 | Land Evidence Date |
| Feb 05, 2018 | Plans Received |