| Action Date | Action Description |
|---|---|
| Jun 23, 2016 | Assent Application Received |
| Jun 24, 2016 | Administrative Review for Completeness |
| Jun 24, 2016 | Team Review for Completeness |
| Jun 24, 2016 | Team Review for Completeness |
| Jun 24, 2016 | Application Accepted |
| Jun 29, 2016 | Correspondence Received |
| Jul 25, 2016 | 30 day Public Notice Issued |
| Aug 25, 2016 | Public Notice End Date |
| Aug 25, 2016 | Plans Received |
| Sep 07, 2016 | HPHC Historical Preservation No Effect |
| Oct 31, 2016 | Additional Information Received |
| Nov 21, 2016 | Biologist Report |
| Nov 23, 2016 | Engineering Report |
| Nov 29, 2016 | Mail Agenda Notice |
| Nov 30, 2016 | Executive Signoff of Staff Reports |
| Dec 13, 2016 | Semi-Monthly Meeting Date Scheduled |
| Dec 13, 2016 | Council Approval Granted |
| Dec 15, 2016 | Stipulation Package from Biologist |
| Dec 15, 2016 | Stipulation Package by Engineer |
| Jan 04, 2017 | Typist for Processing |
| Jan 04, 2017 | US Army Corps of Engineers Approval Received |
| Jan 04, 2017 | Executive Sign Off |
| Jan 04, 2017 | Sent to Photo Copy |
| Jan 04, 2017 | Permit Issued |
| Feb 09, 2017 | Land Evidence Date |
| Jun 30, 2017 | Comments Received |
| Jan 17, 2018 | US Army Corps of Engineers Approval Received |