| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jul 28, 2016 | Assent Application Received |
| Jul 29, 2016 | Administrative Review for Completeness |
| Aug 10, 2016 | Team Review for Completeness |
| Aug 10, 2016 | Deficient Application - Owner Notification Sent |
| Aug 23, 2016 | Deficient Application Picked Up |
| Oct 31, 2016 | Deficiency Response Received |
| Nov 01, 2016 | Team Review for Completeness |
| Nov 02, 2016 | Application Accepted |
| Nov 02, 2016 | Category A* (Docks) |
| Nov 02, 2016 | Team Review for Completeness |
| Nov 10, 2016 | HPHC Historical Preservation No Effect |
| Nov 30, 2016 | 30 day Public Notice Issued |
| Dec 30, 2016 | Public Notice End Date |
| Jan 23, 2017 | US Army Corps of Engineers Approval Received |
| Jan 24, 2017 | Typist for Processing |
| Jan 24, 2017 | Sent to Photo Copy |
| Jan 24, 2017 | Permit Issued |
| Jan 24, 2017 | Biologist Report |
| Mar 22, 2017 | Land Evidence Date |