| Action Date | Action Description |
|---|---|
| Ready to Schedule Semi-Monthly Meeting | |
| May 05, 2017 | Assent Application Received |
| May 08, 2017 | Administrative Review for Completeness |
| May 10, 2017 | Team Review for Completeness |
| May 10, 2017 | Team Review for Completeness |
| May 10, 2017 | Application Accepted |
| May 15, 2017 | Correspondence Mailed/Faxed/E-mailed |
| Jun 05, 2017 | HPHC Historical Preservation No Effect |
| Jun 12, 2017 | Plans Received |
| Jun 12, 2017 | 30 day Public Notice Issued |
| Jul 11, 2017 | Objections/Comments Received |
| Jul 12, 2017 | Public Notice End Date |
| Jul 21, 2017 | Public Notice End Date Extension Granted |
| Jul 24, 2017 | Objections/Comments Received |
| Sep 01, 2017 | Additional Information Requested from Applicant |
| Oct 16, 2017 | Plans Received |
| Nov 07, 2017 | Supervisor Biologist SignOff |
| Nov 10, 2017 | Supervisor Engineer SignOff |
| Nov 30, 2017 | Executive Signoff of Staff Reports |
| Dec 01, 2017 | Biologist Report |